E16 Bagn-Bjørgo, Norway

E16 Bagn–Bjørgo is an 11.1 km stretch of the main road between Norway’s capitol Oslo and the second largest city, Bergen. The project will significantly improve the safety of travellers compared to driving conditions on the old road.

CEEQUAL Excellent (76.0%) – Construction Award
Version 5, March 2018 | Between Bagn and Klosbøle, Norway

Assessors: Henning Fjeldheim, Skanska Norge AS
Verifier: John Logan, McLaughlin & Harvey
ConstructorSkanska Norge AS

.

Project Summary

E16 Bagn–Bjørgo is an 11.1 km stretch of the main road between Norway’s capitol Oslo and the second largest city, Bergen. The project will significantly improve the safety of travellers compared to driving conditions on the old road.

The major parts of the project are:

  • The 4.3 km tunnel from Bagn to Klosbøle
  • 4 bridges
  • Improvements to the existing stretch of road from Klosbøle to Bjørgo

Due to the collaboration between the client Statens Vegvesen and the contractor Skanska, the project was finished 10 months before originally planned. The contract value was 73.5 M EUR.

Challenges

The main sustainability challenges for the project were:

  • Dust, noise and vibrations
  • Emissions to the water environment
  • Invasive and protected species
  • Energy consumption during construction
  • Materials and waste

These issues were handled through planning, measurements, corrective actions if necessary and follow-up. During the duration of the projects several corrective actions were made. For example related to dust from site traffic and emissions to the water environment. At the end of the project, no there had been only minor incidents with no lasting negative impacts to neighbours or the environment.

By using CEEQUAL in this project, our mindset is changed towards seeking sustainability and environmental gains. This mindset is brought with us to future projects.

Therese Høy (project manager, Statens Vegvesen)

Benefits

For the project in isolation and the industry as a whole, E16 Bagn-Bjørgo is important as it is the first road-project with a CEEQUAL certification. It is also the first project with a CEEQUAL certification for one of the major clients in the civil industry in Norway. This signals an important shift and an opportunity for using CEEQUAL as a common platform for improving sustainability in a more effective way on an industry level.

The use of CEEQUAL influenced the project mainly through creating awareness of sustainability and actively identifying possibilities for improvement with sustainability performance in mind. For example considering alternative construction methods and creating additional value for the local community.

Photo: Bjarte Næss/Skanska

Which elements of the project highlighted best practice and innovation?

The following examples highlight the projects best practice and innovation:

  • The alternative suggestion for construction method which reduced the construction period by 10 months and reduced the diesel consumption by 72,000 litres
  • Creating value for the local community by using 190,000 m3 of excavated rock to build a local road and elevating the local soccer pitch to avoid damage from flooding
  • Reducing waste and creating value for the local community by reusing formworks as bridges in the local cross-country trails

Statens Vegvesen and Skanska have a history of working thoroughly with sustainability. Implementing CEEQUAL into the E16 Bagn-Bjørgo project has triggered us to establish strech targets for sustainability and in bringing this aspect into everyday decision making.

Bjarte Næss (Project Manager, Skanska)

Did CEEQUAL represent good value for money?

The awareness-effect that CEEQUAL brings into a project is a very important and valuable. It reduces risk of negative impacts on the environment and increases the potential for suggestions to improve the performance. It is however difficult to quantify in economic terms in retrospect.

CEEQUAL Section Specific Achievements

Project Management

As a result of the choice of going for a CEEQUAL certification of the project, the project team was made more aware of the environmental issues. This had a positive effect as the importance of environmental issues were made clear to everyone through the embodiment in CEEQUAL.

Land Use and Landscape

In the planning of the project it was decided that the dimensioning criteria for flooding should be a downpour scenario occurring every 200-years. This is stricter than the baseline criteria and resulted in the following enhancements:

  • The area around and close to the columns carrying the original Bagn bridge were stone pitched.
  • The river bank was elevated with surplus excavated rock from the tunnel.
    Larger span between the axes on the bridge than normal, to reduce the risk of congestion of water due to a narrower passage.
  • It was decided not to demolish the old bridge over the Begna river. The columns contribute to regulate the velocity of the water. If they were to be removed, it would have resulted in a significant larger local risk for erosion in a flooding scenario
  • Establishing energy absorbing structures downstream where waterways crossed under the road

Physical Resources – Use and Management (Energy, Water, Materials, Waste)

During the construction phase the planned 250 W NAH lighting in the tunnel was replaced with 129 W LED which resulted in a reduced annual energy consumption of more than 100,000 kWh.

190,000 m3 of excavated rock was used locally to construct a road and elevate a sporting field to avoid flooding.

Used formworks were given to a local cross-country skiing organisation to use as creek-crossings, both reducing waste and creating value for the local community.

The construction period was reduced by 10 months compared to what was originally planned. The alternative construction method resulted in amongst other things a reduction of 72,000 litres of diesel for movement of blasted rock by trucks.

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

Skonviksvagen-featured

Stockholm Metro Nacka project awarded Excellent

The Stockholm Metro Nacka Extension is awarded Excellent, showing Stockholm's commitment to sustainable urban development ...
breeam-infrastructure-stockholm-metro-extension-sofia

Stockholm Metro Sofia access tunnel a BREEAM Infrastructure success

BREEAM Infrastructure is helping Stockholm expand it's Metro to boost public transport and support sustainable urban growth ...
Stockholm Extended Metro access tunnel Sundstabacken achieves CEEQUAL Excellent rating

Stockholm Extended Metro access tunnel Sundstabacken achieves CEEQUAL Excellent rating

The Stockholm Metro extension aims to boost public transport capacity by growing the system. Building metro infrastructure in a dense ...
E08-Forberedende-arbeider-BREEAM Infrastructure

Preparatory works for the new water treatment system in Oslo achieves BREEAM Infrastructure Excellent rating

The preparatory works for the new water treatment system in Oslo, ordered by 2028 achieves BREEAM Infrastructure Excellent ...
Ramsdal bridge BREEAM Infrastructure

E39 Mandal øst – Mandal

E39 Mandal East- Mandal city consist of a 7 km long four lane highway that together with the new E39 ...
BREEAM Infrastructure Bybanen D18 Sykkelvei Kronstadtunnelen

Bybanen D18 Sykkelvei Kronstadtunnelen

Project D18 Sykkelvei Kronstadtunnelen is part of the Bybanen-light rail construction stage 4 development scheme. This is the largest development ...

Get in touch

Contact us now or call us on +443330147880 if you would like to talk to our team about how CEEQUAL can support you.