Sea filling winter conditions

E16 Kvamskleiva

Sea filling winter conditions

BREEAM Infrastructure Very Good – Construction Only Assessment

Version 6, 2023 | Norway

Assessed by: Elisabeth Larsen, Inger Aaberg- Hæhre Entreprenør AS
Verified by: Catherine Pinney – CERES Associates
Client:Statens Vegvesen
Contractor: Hæhre Entreprenør AS

E16 Kvamskleiva was mainly a rock slide protection project in an area with steep mountain sides and frequent ice- and rock slides. The road is one of the main roads between eastern and western Norway and between the country’s two largest cities, Oslo and Bergen. The project was wanted by both the local community of Valdres and other travellers, as the stretch of the road was known as “the most dangerous road in Valdres.” Hæhre Entreprenør signed the contract with the Client Norwegian Public Road Administration (Statens vegvesen) in October 2020, and the project was executed as an EPC contract. Total road length is 5.4 km, including a 1.8 km tunnel. Physical work started in November 2020.

Tunneling works - BREEAM Infrastructure

In the most dangerous segment, the new road runs through a tunnel. Another part of the road is moved to a sea filling, making space for a rockfall protection embankment between the steep mountain sides and the road.

In addition to the road and tunnel, one main component of the project was the sea filling in Norsvinsfjorden, a large lake parallel to the existing road. The sea filling was constructed by tunnel rocks and was subject to strict environmental requirement because of ecological qualities of the lake and nesting birds.

Large quantities of rocks and soil (approximately 700 000 m3) were handled and transported without major disruptions to road users. This was successful because of great planning and, in particular, complex phase plans that focused on third parties and their safety. Almost no soil or rock was transported on the public road. Despite limited space, we were able to transport the materials through the project site.

Sea filling with silt curtain - BREEAM Infrastructure

Metrics

Embodied carbon emissions 22 800 000 kgCO2 equivalent 22% reduction achieved
Re-used excavated material 713 190 m3 100% of total material used
Waste diverted from landfill 302 tonnes 97% of total waste

 

Financial Benefits

Did the use of BREEAM Infrastructure deliver any financial benefits?

Reuse of all soil and rock masses can partly be attributed to the use of BREEAM Infrastructure and more awareness of resource use.

Estimated savings that can be attributed to BREEAM Infrastructure.

We saved approximately £1,3 million (17 million NOK) through improved soil handling.

In your view, has BREEAM Infrastructure represented value for money?

Awareness of sustainability and opportunities related to efficient resource use.

Environmental monitoring - BREEAM Infrastructure

Achievements

Transportation

Detailed planning of project phases and logistics enabled soil and rock transportation within the project area. As a result, there was minimal disruption to the public traffic flow and a safer solution for the community.

Resources

We managed 100% reuse of soil and blasted rock, through planning and focus. Identification of reuse options for lightly contaminated soil in the tunnel with no migration risk, and an application process to the authorities, made it possible to reuse soil that initially, according to requirements, was expected to be deposited on a landfill.

Landscape and historic environment

The first driveable road between eastern and western part of Norway was built in 1790 and is now called Kongeveien (the King’s road). Remains of the road is a road historical heritage asset that now serves as a popular hiking trail. During the project, part of the old road was reconstructed in order to connect it to remaining parts.

Further Information

What were the main challenges for the project / contract and how were these overcome?

One of the main challenges in the project was to keep the tight schedule in an area with harsh winter conditions of cold temperatures, high winds, and risk of ice- and rockslides. Large amounts of soil and rock was handled and transported in a small area close to and across the existing road, all while keeping the road open to the public. There were only minor disruptions to traffic due to blasting.

What were the drivers and perceived benefits for undertaking a BREEAM Infrastructure assessment on this project / contract?

The motivation was to increase the quality of the project and to broaden its definition of sustainability. The BREEAM assessment provided motivation and tools for improving how we document what we actually do to reduce environmental impact, use our resources efficiently, and minimize the negative consequences for the community during the construction period.

How did the use of BREEAM Infrastructure influence the outcomes of the project / contract? What was done differently because of the BREEAM Infrastructure process?

The use of BREEAM Infrastructure influenced the planning and optimalization of resource use, both regarding natural resources in the project and material use. Even though we always focus on having a good relationship to the local community during our projects, we had an extra awareness at Kvamskleiva about two-way dialogue and facilitation of engagement, despite the constraints imposed by the COVID-19 pandemic.

What elements of this project / contract highlight best practice and innovation?

The planning and performance of the mass transportation highlights best practice and was a major reason why we completed the project three months early.

Fish hotel and rockfall protection - BREEAM Infrastructure

Quotes

Together with Statens Vegvesen, we have succeeded in the planning of the project to allow for an earlier opening of the road. Usually, we want to start tunnel works during summertime. In Kvamskleiva, we started in December.

Jan Lima, Project Manager, Hæhre Entreprenør

Statens Vegvesen and Hæhre have achieved this through good planning, good cooperation and above all a lot of successful work.

State Secretary at the Ministry of Transport, Jacob Bjelland (at the opening celebration)

Cultural heritage - milestone - BREEAM Infrastructure

BREEAM Infrastructure insights and case studies

Browse the latest insights, thinking and case studies from BREEAM Infrastructure

 

Skonviksvagen-featured

Stockholm Metro Nacka project awarded Excellent

The Stockholm Metro Nacka Extension is awarded Excellent, showing Stockholm's commitment to sustainable urban development ...
breeam-infrastructure-stockholm-metro-extension-sofia

Stockholm Metro Sofia access tunnel a BREEAM Infrastructure success

BREEAM Infrastructure is helping Stockholm expand it's Metro to boost public transport and support sustainable urban growth ...
Stockholm Extended Metro access tunnel Sundstabacken achieves CEEQUAL Excellent rating

Stockholm Extended Metro access tunnel Sundstabacken achieves CEEQUAL Excellent rating

The Stockholm Metro extension aims to boost public transport capacity by growing the system. Building metro infrastructure in a dense ...
E08-Forberedende-arbeider-BREEAM Infrastructure

Preparatory works for the new water treatment system in Oslo achieves BREEAM Infrastructure Excellent rating

The preparatory works for the new water treatment system in Oslo, ordered by 2028 achieves BREEAM Infrastructure Excellent ...
Ramsdal bridge BREEAM Infrastructure

E39 Mandal øst – Mandal

E39 Mandal East- Mandal city consist of a 7 km long four lane highway that together with the new E39 ...
BREEAM Infrastructure Bybanen D18 Sykkelvei Kronstadtunnelen

Bybanen D18 Sykkelvei Kronstadtunnelen

Project D18 Sykkelvei Kronstadtunnelen is part of the Bybanen-light rail construction stage 4 development scheme. This is the largest development ...

Get in touch

Contact us now or call us on +443330147880 if you would like to talk to our team about how BREEAM Infrastructure can support you.